TOPIC: UNDER CAUSE OF ACTION, IN CONTRAST WITH
THE BLOSSOM CASE, THIS IS A CASE WHERE THE PRINCIPLE OF ANTICIPATORY BREACH
CANNOT BE APPLIED
DANFOSS, INC. V. CONTINENTAL CEMENT CORP., G.R. NO.
143788, 9/9/05
NATURE OF THE CASE: The CA affirmed the decision of the
RTC that the CCC’s (herein respondent) complaint for damages against Danfoss.
So, the case was elevated to the Supreme Court on appeal of the said ruling of
the CA and the CA’s denial for Danfoss’ motion for reconsideration.
FACTS: Mechatronics Instruments and Controls, Inc.
(MINCI) is an agent of Danfoss, Inc.’s products here in the Philippines. On
September 1997, CCC ordered two unit 132 KW Danfoss Brand Frequency
Converter/Inverter from MINCI to be used in the Finish Mill of its Cement Plant
in Bulacan. In the terms of conditions of the original purchase order, the two
unit Frequency Converter shall be delivered by Danfoss within 8 to 10 weeks from the opening of the
letter of credit. The letter of credit opened by CCC in favour of Danfoss on
September 9, 1997.
On September 17, 1997, MINCI informed
CCC that its order are already ready for shipment and MINCI requested to amend
the letter of credit changing the port of origin/loading from Singapore to
Denmark (Singapore is the Asian Regional Office of Danfoss, the Head Office of
the company is Denmark). CCC complied and the port of origin in the letter of
credit was changed.
On November 6, 1997, MINCI relayed
to CCC that Danfoss Inc. was still checking the status of their order. CCC
replied that every delay in the delivery of the order will cause loss to their
company, so CCC requested for early work out and immediate shipment to avoid
further loss.
But, on November 9, 1997, Danfoss
Inc. informed MINCI through fax, that the reason for the delivery problems was
that some of the supplied components for the new VLT 5000 series (this may be a
part of the converter which is the subject thing in this case or a machine to
create the converter) did not meet the agreed quality standard. So, Danfoss was
canvassing for another supplier for the said VLT 5000 series. In the fax, there
was no clear message as to when normal production will resume.
Upon receiving the relayed
information, CCC surmised that Danfoss would not be able to deliver their
order. There was also no definite commitment of the delivery from Danfoss and
MINCI, so CCC informed MINCI that they intend to cancel its order. The order
was cancelled on November 13, 1997.
Hence the complaint for damages
filed by CCC with the RTC of Quezon City against Danfoss and MINCI on November
5, 1998. In reply, Danfoss filed a motion to dismiss the complaint.
CCC: Due to the
“impending” delay in the delivery of its order, it suffered more than P8
million and was compelled to look for another supplier.
Danfoss: The case should be
dismissed on the ground that it did not state a cause of action.
1)
The
letter of credit was opened on September 9, 1997, so, since the agreed delivery
period is 8 to 10 weeks from the opening of the letter of credit, the due date
is until November 19, 1997.
2)
Although
Danfoss was having a problem with its supplier prior to CCC’s cancellation of its order, CCC only
surmised that Danfoss could not deliver within the due date agreed upon.
3)
Neither
Danfoss nor CCC agreed to change the date of delivery. Only the port of origin
was changed in the letter of credit. Danfoss has until November 19, 1997 to
deliver the order, CCC cancelled the order on November 13, 1997.
4)
CCC
never made an extrajudicial demand for the delivery of its order on its due
date as it cancelled the order before the due date.
5)
Damages
sought for by CCC could not have accrued yet since the order was cancelled
before the delivery was actually delayed.
RTC: Judgment in favor of
CCC. According to the RTC:
“...the issue of whether or not the
defendants incur delay in the delivery of the equipment in question within the
period stipulated is a debatable question which necessitates actual trial on
the merits where the parties have to adduce evidence in support of their
respective stance.
While the defendants contend that
the stipulated period of delivery had not lapsed yet when the plaintiff
cancelled its order of the two equipments in question as the cancellation took
place seven (7) days before the expiry date of the defendants’ obligation to
deliver, the plaintiff’s position is that the acts of the defendants had made
compliance with their obligation to deliver within the period stipulated,
impossible, hence, there was no need for a demand as the law provides that
“when demand would be useless, as when the obligor has rendered it beyond his
power to perform.” The plaintiff’s
contention if properly and strongly supported by evidence during the hearing of
the merits of the case may well negates (sic) the defendant’s contrary stand.”
CA: Affirmed the
decision of the RTC and denied the Motion for Reconsideration of Danfoss.
ISSUE: WON there was a cause of action in the
complaint filed by CCC against Danfoss and WON the principle of anticipatory
breach can be applied in the case.
HELD: No, there was no cause of action in the complaint for
damages filed by CCC.
“In order to sustain
a dismissal on the ground of lack of cause of action, the insufficiency must
appear on the face of the complaint. And
the test of the sufficiency of the facts alleged in the complaint to constitute
a cause of action is whether or not, admitting the facts alleged, the court can
render a valid judgment thereon in accordance with the prayer of the complaint.
For this purpose, the motion to dismiss must hypothetically admit the truth of
the facts alleged in the complaint.”
The RTC erred in ruling that “the
issue of whether or not the defendants incurred delay in the delivery of the
equipment within the period stipulated was a debatable question.” How could
Danfoss be liable for damages when Danfoss had not yet breached his obligation
to deliver the order of CCC, aside from the fact that the obligation was
already negated when CCC cancelled the order before the prestation became due
and demandable? Thus, there was no breach and there was no damage caused by
Danfoss.
The principle of anticipatory breach
cannot be applied here because the obligation was single and indivisible – to
deliver two units of frequency converter by November 19, 1997. There was no
showing that Danfoss refused to deliver, and on the contrary, Danfoss made an
effort to make good in its obligation by looking for other suppliers who could
provide the parts needed to make the timely delivery of the order. Thus, the
case was prematurely filed.
CCC’s fear that Danfoss might not be
able to deliver its order on time was not the cause of action referred to by
the Rules and jurisprudence.
PETITION GRANTED. THE CA’S DECISIONS
ARE REVERSED AND SET ASIDE.
No comments:
Post a Comment